Welcome to Single Window Clearance Portal

(under "Ease of Doing Business" Project)

A National E-Governance Project of G.O.I
About Us

The GoI has undertaken the “Ease of Doing Business (EoDB)” project all over the country to facilitate a “Business friendly environment”, so that Entrepreneurs can Establish and Operate Business enterprises in the various States, easily and quickly. One major component of EoDB project is the establishment of “Single Window Clearance (SWC) portal” by states so that all clearances provided by States to business enterprises are brought under a Single System, which will reduce the hardships faced by business community in the country.

In A & N Islands, District Industries Centre (DIC) is the Nodal department for implementing EoDB project. The SWC portal for A & N Admin has been has been designed and developed by NIC, Port Blair in coordination with DIC and various departments of A & N Admin. The SWC portal has been developed by NIC after analysis of efforts taken by other States in this direction and following Guidelines of GoI for EoDB project and SWC portal.

Know More

Services

Clearances

Procedures to avail Online Clearance

Clearance Matrix

Check all the Clearance Available.

Track Status

You can track status of Applications for CAF, Clearances

Digital Locker

Access all the Forms,Documents,Etc..

Transaction Chart will load here!
Transaction Chart will load here!
Transaction Chart will load here!
Consolidated Chart will load here!
Particulars Details
Time Limit prescribed as per the Public Services Guarantee Act 15 Days
Total Number of application received 15061
Total Number of application approved 12552
Average time taken to obtain registration/renewal 35 Days
Median time taken to obtain registration/renewal 15 Days
Minimum time taken to obtain registration/renewal WITH IN A DAY
Maximum time taken to obtain registration/renewal 1151 Days
Particulars Details
Time Limit prescribed as per the Public Services Guarantee Act 15 Days
Total Number of application received 1315
Total Number of application approved 545
Average time taken to obtain registration/renewal 35 Days
Median time taken to obtain registration/renewal 22 Days
Minimum time taken to obtain registration/renewal 2 Days
Maximum time taken to obtain registration/renewal 668 Days
Particulars Details
Time Limit prescribed as per the Public Services Guarantee Act 30 Days
Total Number of application received 1495
Total Number of application approved 477
Average time taken to obtain connection 60 Days
Median time taken to obtain Connection 50 Days
Minimum time taken to obtain connection WITH IN A DAY
Maximum time taken to obtain connection 181 Days