Building Plan Services

BUILDING PLAN APPROVAL

S.No Nature of Work Time of Attending
1. Enquiry All working days 10.00 a.m to 12.00 noon
2. Issue of Application forms at single window counter @ 10/- All working days between 10.00 a.m to 12.00 noon and 2.00 p.m to 4.30 pm
3. Communication of deficiencies Within 30 days
4. All inquires including advise on deficiencies in applications documents
will be attended across the table at building cell
Between 1.00 a.m to 12.00 noon on working days
5. Challan for fees/other charges will be issued by Head Clerk, Tax Section Between 10.00 am to 12.00 noon on working days
6. Final decision on applications for sanction of building plans Within 60 days after submission of Building plan
7. Communication of decision on revalidation of buildings plans Within 30 days
8. Communication decision on completion certificate/plans Within 30 days

TO BE CONTACTED

S.No Name Of The Official Designation Contact Number Contact Office
1. Shri. Gautam Dutta Building Officer (O) 230236 Ext.366 Building Cell
2. Shri.Jepson Deniel Assistant Engineer (Planning (i/c) (O) 230236 Ext.327
(M) 9434287193
Planning Section
3. Shri.P.R.C.Nair Revenue Officer (O) 230236 Ext.330 Revenue Section
S.No Name Of The Official Designation Contact Number Contact Office Jurisdiction/Ward
1. Shri.Ramanus Toppo Building Inspector (O)230236 Building Cell Ward 1 to 6
2. Shri.N.Shajee Building Inspector (O) 230236 Ext.366 Building Cell Ward 7 to 11 and 18
3. Shri.Raj Kumar Building Inspector (O) 230236 Ext.366 Building Cell Ward 12 to 17

DOCUMENT TO BE REQUIRED FOR Building Approval

S.No Documents Required
1. Revenue map
2. Record Entry
3. Building plan duly signed by the Registered Architect/ Engineer and License Supervisor registered under the Municipal Council as per Building Bye-laws
4. Structural drawing duly signed by the Registered Engineer registered under the Municipal Council as per Building Bye-laws.