12th FIVE YEAR PLAN SCHEME -CENTRAL SECTOR

Sl.No. 

                                                                                                    Name of Schemes

12th plan Proposals

Estimated Cost (Rs in Crores) 12th plan Outlay (Rs in Crores)

A

Andaman & Nicobar Islands

I

ON GOING SCHEMES 

1

 Development of foreshore area at Jungighat harbour, Phase - I

17.44 0.02

2

 Reconstruction of office building complex for ALHW

11.76 0.69

3

Construction of Finger Jetties under development of Junglighat Harbour Phase - II

78.93 25.95

4

Construction of Marine Hard / Jetty at Chowra

14.98 5.63

5

Construction of jetty at Gandhi Nagar in GNI

14.99 3.71

6

Replenishing of damaged Breakwater and approach to wharf at Hut Bay in Little Andaman

80.98 19.30

7

Acquisition of two number tug

90.00 88.85

8

Repleneshing of breakwater with Tetrapods & Construction of wave deflection wall at Mus in Carnicobar

90.00 0.52

9

Construction of Shore Protection Work at Campbell Bay

46.48 0.50

10

Conducting Non Destructive testing, Phase-I

0.55 0.10

11

 Conducting Non Destructive testing, Phase-II

2.04 0.20

12

 Construction Of Marine Hard at Campbell Bay

8.86 1.45

13

 Construction Of Marine Hard at Long Island

5.38 0.39
14

 Construction Of Vehicle Ferry Ramp at Havelock

4.54 0.32

II

NEW SCHEMES

1

 Extension of Break water by 300 mtrs at Campbell Bay in  Great Nicobar.

250.00 1.0

2

 Construction and development of Berth for container vessels of 14m draft at Blair Reef in Port Blair

300.00 1.0

3

 Replacement & up-gradation  of Cargo Handling equipments in  various ports of A&N Islands

39.02 39.02

4

 Additional approach to Wharf at Hut Bay

45.00 1.00

5

 Development of sea route to Baratang in A&N Islands

45.16 45.16
  Total for Andaman & Nicobar Islands.   234.81
B

Lakshadweep Islands

I

ON GOING SCHEMES 

1

 Providing eastern side embarkation facilities at Amini Islands

21.51 0.09

2

 Providing eastern side embarkation facilities at Agathi Islands.

19.48 0.06

3

 Providing eastern side embarkation facilities at Minicoy Islands.

19.86 2.25

4

 Providing eastern side embarkation facilities at Kavaratti Islands.

20.44 0.39

5

 Procurement of Cutter Suction Dredger for Lakshdweep Ports

4.93 3.91

II

NEW SCHEMES

1

 Extension of 3rd stage Breakwater at Androth

425.00

132.00

2

 Feasibility studies for Construction of Breakwaters at Amini, Kadmath, Kiltan, Chetlat & Bitra

6.00

1.00

3

 Providing Slipway with workshop facilities at Kavaratti, Minicoy, Kadmath, Agathi, Chetlath

20.00

10.00

4

 Replacement & up-gradation  of Cargo Handling equipments in  various ports of Lakshadweep

1.91

1.91

5

 Dredging in the Navigational Channels & Harbours and  providing Navigational Aids in Lakshadweep

50.00

10.00

6

 Feasibility studies in connection with recommendations of  Capt. PVK Mohan Committee for improvement to berthing in  easternside jetties at Lakshadweep, including deployment of  wave rider buoys, fixing of mooring buoys & construction of  curtain walls

6.00

2.00

   Total For Lakshadweep Islands  

163.61

C

 ESTABLISHMENT  

44.38

   GROSS TOTAL (A+B+C)  

442.80